Aug 18, 2017 | Building Program Progress
The building process at 2092 Beach Boulevard, the site of our new multi-purpose building, is on pace for an end-August conclusions. We will begin the transition to the building when we get the various government sign-offs starting in September. Tentative plans call...
Aug 9, 2017 | Building Program Progress
Construction Schedule – Church of Our Savior 8-8-17Construction of the Church of Our Savior multi-purpose building proceeds on schedule. The adjacent photographs taken midday on 9 August, show the exterior of the new building in the late stages of construction....
Aug 2, 2017 | Building Program Progress
In general, the Church of Our Savior Multi-purpose building at 2092 Beach Boulevard is at the end stages of construction and approximately on schedule. The estimated completion date is by the end of August (current month) assuming all continues to go well. A major...
Jul 11, 2017 | Building Program Progress
In general, our new building is proceeding according to the construction schedule and should be completed by the end of August, 2017. Some current activities: • As seen in the adjacent photo, stripping to hold the insulation and exterior trim is being applied to the...
Jun 26, 2017 | Building Program Progress
The Church of Our Savior multi-purpose building continues to take shape. Recent activities: • The fire sprinkler system was installed and passed a pressure test on Friday, 23rd of June. • The curbs have been installed throughout the road and parking lot. (See adjacent...
May 26, 2017 | Building Program Progress
The second floor Insulated Concrete Forms (ICF) walls have been erected and ready mix poured to complete the process. Pre-fabricated trusses for the roof have been lifted by a crane and fastened into place. The adjacent images show the building status on Friday, May...