The ceiling for the first floor was poured on Tuesday, the second of May 2017. Shown below is the progress on a.m. of 9 May showing the forms for the Insulated Concrete Forms (ICF) being mounted into place. The view is to the North from the church’s southern lot. As with the first floor, when the ICF is in place and trimmed, the ready-mix will be poured, forming a strong, energy efficient wall.
The second image is a view of the stairwell on the first floor of our new building. The shaft for the lift is shown at the right side of the picture.
The framing for the superstructure will commence upon completion of the pouring of the second floor. The construction is on track at this point, with work projected to be completed by end August, 2017.